Teraco Isando Campus (JB1 + JB3 + JB5)
Also known as Teraco Isando Campus, Teraco JB1 + JB3 + JB5, Teraco JB1, Teraco JB3, Teraco Johannesburg Isando
- Status
- Operational
- Location
- Isando, South Africa
- Operator
- Teraco
- IT load
- 40 MW running
- Timeline
- Not disclosed
- Last verified
Overview
This record covers Teraco's Isando campus, not a single JB1 building. The 2023 technical sheet in data/sources/2023-Teraco-Tech-Spec-Isando-Campus.pdf is titled "JB1 + JB3 Isando Campus"; Teraco's current Johannesburg page presents the Isando campus as JB1 + JB3 + JB5.
The technical sheet reports 45,000 square meters of total space, 20,000 square meters of white space, 80MVA total power, and 40MVA available IT power load across the data centre footprint. Because the schema has MW fields but no MVA fields, the power figures are recorded as MW-equivalent with notes.
Cloud on-ramps and provider names are treated as connectivity/ecosystem evidence, not as proof that the named cloud providers are tenants in this facility.
Capacity
What IT load means- IT load — current
- 40 MW
- The technical sheet reports 40MVA available IT power load across the data centre footprint; stored as MW-equivalent pending schema support for MVA.
- reported Source [s2]
- Total facility power
- 80 MW
- The technical sheet reports 80MVA total power; stored as MW-equivalent pending schema support for MVA.
- reported Source [s2]
- Building area
- 45,000 m²
- The technical sheet reports over 45,000 square meters of total space.
- reported Source [s2]
Infrastructure
Tier certification explained- Cooling
- Not disclosed
- The technical sheet reports N+1 cooling redundancy and environmental controls but does not identify a cooling technology.
- reported Source [s2]
- Connectivity
- NAPAfrica Internet Exchange, Africa Cloud Exchange, Cloud on-ramps for Amazon, Google, Huawei, Microsoft Azure, Oracle, and VMware Cloud Verified providers, Carrier-neutral network and interconnection hub
- reported Source [s1] Source [s2]
- AI cooling readiness
- Not assessed
Cooling adequacy for AI workloads has not been independently assessed for this facility.
AI racks draw around 100 kW each, about ten times a conventional rack, so rack-level liquid cooling is the key differentiator. Training versus inference
Power
PPAs and wheeling- Backup
- diesel
- The technical sheet reports diesel backup generators with a minimum 48 hours of fuel under full-load design conditions.
- confirmed Source [s2]
Governance
Data residency explainedWorkloads
Training versus inference- General cloud
- Colocation
Teraco describes the Isando campus as a carrier-neutral colocation and interconnection hub with cloud on-ramps. No public source reviewed here confirms dedicated AI training capacity, GPU counts, or active liquid-cooled AI deployments.
Sources
How sources are ranked- [s1]
- [s2] Teraco JB1 + JB3 Isando Campus technical specifications, PDF retrieved from the Equinix/Teraco site and stored in data/sources/2023-Teraco-Tech-Spec-Isando-Campus.pdf, Teraco
company official Retrieved 29 June 2026 Not yet archived
What these source types mean
- company official
- Press releases, investor relations filings, and product pages from the operating company.