Teraco CT1 Rondebosch

Expanding Small-scale

Also known as: Teraco CT1 · Teraco Cape Town 1 · CT1 Rondebosch

Cape Town, Western Cape, ZA city coords Last verified: 29 June 2026 Report a correction

Overview

This record replaces the prior inaccurate `equinix-ct1-cape-town` identity. The Daily Maverick article identifies a 60MW Cape Town expansion as Teraco's project and links to Teraco's CT1 Rondebosch announcement. Teraco's own announcement reports CT1 current critical IT load of 3MW and a further 2MW expansion, so the structured CT1 capacity fields use Teraco's company-official figures. Cooling method, water demand, and AI-specific capacity remain unconfirmed in the reviewed sources.
IT load — full buildout
5 MW

Teraco reports CT1 will expand from 3MW by a further 2MW of critical IT load.

confirmed [s1] [s2]
IT load — current
3 MW
confirmed [s2]
Building area
3,500 m²

Teraco reports 2,500 square meters of current data halls plus a 1,000 square meter expansion.

confirmed [s2]

Power in context

5 MW IT load ≈ 14,500 South African households (avg 250 kWh/month)

0.3% of Cape Town's peak grid demand (1,676 MW)

0.02% of South Africa's effective grid capacity (~30 GW available)

Comparable to a mid-size cloud data centre

About IT load · Announced vs operational MW

Infrastructure

Tier guide →
AI cooling readiness
Not assessed

Cooling adequacy for AI workloads has not been independently assessed for this facility.

AI data centres require ~100 kW/rack (10× conventional). Liquid cooling at rack level is the key differentiator. Learn more →

Grid utility
City of Cape Town
reported [s1]
Grid carbon intensity
900 g CO₂/kWh

City of Cape Town large loads are ultimately Eskom-backed; grid-level figure, not facility-specific.

estimated ≈ [s1]

Grid carbon context

900 g CO₂/kWh — Very high — coal-heavy grid

2.1× the global average (436 g CO₂/kWh, IEA 2022). Compare: France ~60, UK ~175, US ~400 g CO₂/kWh.

Grid-level estimate. PPAs and on-site renewables may reduce the effective carbon footprint.

Water source
unknown
Water stress (WRI)
high

Governance

Data residency →
Jurisdiction
South Africa
confirmed [s1]
Data residency
Data physically resident in South Africa under POPIA jurisdiction

Workload Profile

Training vs inference →
General Cloud Colocation

Carrier-neutral colocation campus operated under the Teraco brand. Daily Maverick describes a 60MW Cape Town expansion by Teraco but does not confirm AI-specific workloads or GPU capacity.

Claims are tracked separately from sourced facts because their status is contested or evolving. A disputed claim is not the same as a confirmed fact.

c1 Capacity expansion
disputed ⚠

Daily Maverick reports a 60MW Teraco expansion in Cape Town and links to the CT1 Rondebosch announcement. Teraco's own CT1 release reports 3MW current critical IT load plus a 2MW expansion, not 60MW at CT1. The structured capacity fields follow Teraco's company-official CT1 figures.

First observed: 2026-04-28 Last reviewed: 2026-06-29

Entities

Operator

Teraco

Owner

Digital Realty

Location

Cape Town, Western Cape, ZA

-33.9637, 18.4762

city precision

Status History

  1. expanded

    2025-11-12

    Teraco announced commencement of the CT1 Rondebosch expansion.

  2. operational

    2012-01-01

    Older CT1 facility; exact opening date not verified in the cited sources.

Record

ID
teraco-ct1-rondebosch
First tracked
2026-05-11
Last verified
2026-06-29

Sources

  1. s1
    New data centres set to swallow 34% of Cape Town's current electricity supply — Daily Maverick
    local journalism retrieved 2026-06-29 not yet archived
  2. s2
    Teraco announces CT1 data centre expansion in Rondebosch, Cape Town — Teraco
    company official retrieved 2026-06-29 not yet archived
About these source tiers
local journalism

Local news outlets; variable editorial standards, used for leads and corroboration.

company official

Press releases, investor relations filings, and product pages from the operating company.

Full ranking: Methodology · Glossary

Found an error? Open an issue or pull request on GitHub with the corrected data and a source URL.